To schedule the concurrent program do the following:
The steps are shown in the following screenshot:
- Log in to Oracle with the XXEBS Extending e-Business Suite responsibility.
- Navigate to Submit Requests and submit a single request.
- Select the XXHR First Concurrent Program concurrent program and leave the
Run Date
andOrganization
parameters set to their default values and click on OK: - Now click on the Schedule button. The screen dynamically changes when you click on each item of the Run the Job radio group.
- Click Periodically.
- Set Re-Run to every 1 Day(s).
- Enter an End At value 2 days from the current date.
- Check the Increment date parameters each run.
- Click on OK and the window will close.
- Click on the Submit button and when prompted to submit a new request select No and the form will close down.
- Navigate to View Requests and click on the Find button (to find all requests).
- You should see that the concurrent program we just submitted has submitted two requests. The first will be set to run immediately and the second concurrent program is Pending with a status of Scheduled, as shown in the following screenshot:
You will notice that the date in the Parameters field has automatically been incremented because we checked the Increment date parameters each run checkbox.